Solid Progress in Thar Coalfield Project
2020/07/01  EN_正规赌钱软件app

On June 15 (local time), the first piece of steel structure was successfully hoisted at the Thar Block-1 2X660MW Coal-fired Power Generation Plant, which means that the construction of main buildings came to the stage of steel structure installation. On June 16 (Beijing Time), the first batch of large equipment was ready for shipment in the Port of Shanghai. The shipment of 22 main girders for boilers posed higher requirements on organization and coordination. Thanks to the support from all stakeholders, everything is in smooth progress and the equipment is expected to arrive at the Port Qasim on July 2.