Reconstruction and construction (incineration power generation) PPP project of Dandong Refuse Disposal Plant
The construction site of this project is located in the original refuse landfill in Longmu Village, Tongxing Town, Zhen'an District, Dandong City, which covers an area of about 185,500m?. It is the first waste incineration power generation project in Dandong City, which adopts the mechanical grate boiler process. It can effectively solve the "Besieged by Garbage" problem in Dandong City and assist the establishment of a long-term ecological and environmental protection mechanism in Dandong City.

    · Business Model:BOT

    · Capacity of Disposal:1500t/d


The first waste incineration power generation project in Dandong City

1) SITY2000 incinerator is selected. This grate boiler adopts the most advanced, most mature and most widely used incinerator technology in the world.

2) The plant-level monitoring information system is established to monitor the whole production process and optimize the management in real time.

3) The internationally renowned brands of garbage grab cranes and variable frequency motors are used to save energy sources.


Contact Us
Shanghai Electric Environmental Protection Group
Address:No.1287,West Beijing Road,Jing`an District,Shanghai,China
Post code:200040
Tel: 021-62472277
Fax:021-63516188